NEW LAW LIMITS AMOUNTS RETAINED UNDER CONSTRUCTION CONTRACTS


By Lauren M. Lyon-Collis


During construction of a development project, the owner typically retains a percentage of each progress payment otherwise payable to the contractor. The retained funds are usually released upon substantial completion, with the owner holding back 150% or 200% of the amount necessary to complete “punch-list” items. The industry standard is to retain 10% of the amount of the progress payment otherwise payable. The purpose of this practice is to ensure that if a contractor fails to complete the work correctly, or at all, the owner may use the retained funds to do so.

A recently-adopted Maryland law limits those amounts that may be retained by an owner to guarantee completion of a construction contract. As of October 1, 2008, owners will only be able to retain up to 5% of the amount of each progress payment for certain construction contracts in Maryland. The new law does not apply to contracts under $250,000 or contacts funded through the Department of Housing and Community Development. State regulations presently impose this cap in certain state construction contracts. The new law also applies to the retention of funds by a contractor to guarantee a sub-contractor’s completion of a construction contract.

The new law attempts to balance the interests of contractors and owners, but, in the end, may be unsuccessful. For example, the new law immediately benefits contractors who may need to advance a portion of their own funds to complete the final stage of a project. The change in the law means that an additional 5% of the contract value could be available, lessening the financial impact in those instances when a contractor must pay “out of pocket” in order to complete a construction contract.

While the new law does not apply to contracts under $250,000, the new law does, however, disadvantage owners by limiting funds available to correct or complete unfinished work under affected contracts. Depending upon the type of work and workmanship, the 5% cap on the amount of payments retained may leave owners with insufficient funds to correct or complete unfinished work. Capping the amount of payment retained to half of the industry standard also diminishes the financial penalty that a contractor would experience by simply leaving the job unfinished.

Yet, some protections remain for owners under the law. First, if the owner or contractor determines that the contractor’s performance provides good reason for withholding an additional amount, the new law provides that the owner may exceed the cap. But an owner may not be able to make that determination in time to retain an additional portion of future payments sufficient to protect the owner from the risk of needing to spend additional funds to hire another contractor. While the new law appears to allow owners to unilaterally withhold additional amounts, contractors may have defenses available to them should an owner elect to do so.

Second, the law imposes the 5% cap only where the contractor has provided payment and performance bonds. The purpose of these bonds is to guarantee the contractor’s performance of the work and the payment of subcontractors and sub-subcontractors for labor and materials in the event the contractor’s performance is inadequate or the contractor fails to pay for materials or labor. An owner’s attempt to exercise its remedies under the bonds may require considerable time and expense and bonding companies often have defenses to enforcement of bonds. Thus, an owner may be inclined only to attempt to enforce its rights under the bonds when completion of the construction work will be very expensive. When weighing the possible time and expense to enforce its remedies under the bonds against the time and cost of using one’s own funds to complete the work, the most reasonable option may be to complete the work with the owner’s additional funds “out of pocket” after spending the retained payments.

Thus, by capping the amount of retention proceeds to one-half the industry standard, the new law may reduce the effectiveness of the practice of holding retained funds, both as a protection to owners and an incentive to contractors to complete work.

Lauren M. Lyon-Collis is currently an associate in the Baltimore office of Ballard Spahr Andrews & Ingersoll, LLP